Solar power project takeover - North Macedonia.
Attached are some pictures from PVP as well as used equipment.
Potential consumer to buy the generated electricity - HUPX(h) - 10% for 1 year contract.
FAQs:
1. Duration of the PPA; Is the price fixed or linked to something?
The duration of the redemption is until 31.03.2024 the price is fixed. Price is not fixed it is HUPX (h) -% hire is link for the price https://hupx.hu/en/market-data/dam/historical-data
1 year contract is something normal on Macedonian market.
2. Technical data and features about panels such as Wp/m2, which panel product and
manufacture origin?
All PV Plant is made with same panel same power 545wp from Jetion Solar https://www.jetionsolar.com/en attached is datasheet.
3. Is the land leased or owned by the project company?
Owned by the project company with own property list it can be checked on Katastar web side
4. Does the equipment have a guarantee and for which period of time, or does it have a bank guarantee or reinsurance?
The warranty is shown in data sheets 12 years for PV panels and 5 years for inverters.